McMinnville Water and Light is in the process of designing new conduit and vault systems at various locations around McMinnville:
- Along SE Davis Street, SE Alethea Way, and SE Woodmill Court. Construction of this project is expected to begin in January 2025.
- Along Fenton Street. Construction of this project is expected to begin in March 2025.
- Along Pine Crest and Park Apartments. Construction of this project is expected to begin in summer 2025.
The conduit and vault systems will replace the existing direct bury power lines and will increase the reliability of McMinnville Water and Light’s electric system. These projects are expected to be completed by July 2025