nce the site is ready, the construction phase commences, our team will install the infrastructure as per the approved plan. Here’s what you can expect during this phase:

  • Construction takes place: Our crews will execute the installation as outlined in the approved plan.
  • For electric, contact your local inspection authority: After MW&L completes the electric service installation, your electrician will make the final connection to the meter. You or your electrician must contact your local inspection authority to schedule an inspection of the electrical work your electrician has completed. This step is crucial to ensure that the installation meets all safety and building code requirements.
  • The inspection authority will notify MW&L if you passed inspection: Following the inspection, the local authority will assess the electrical installation. If the work meets the necessary standards, they will issue a passing inspection notification.
  • MW&L will set the meter: Once we receive the notification of the passing inspection from the local authority, we will promptly proceed with setting up the electric meter for your new construction. In most cases, this will be done as early as the next business day after receiving the notification.

At this stage, your new construction will be ready to receive electric service, and you can begin utilizing the power supply for your project.