Organic Valley Water Main Replacement

  • MW&L is installing approximately 880 ft of new 8-inch ductile iron water main within a new 20-foot easement through Organic Valley's property.

 


 

NW Ash Street & NW Coventry Way

11/28/2022: McMinnville Water and Light is finalizing plans for the installation of new conduit and vaults on NW Ash Street and NW Coventry Way.  The project will improve the reliability of MW&L’s distribution system.  Once the plans are complete, MWL will select a contractor.  The installation will be by means of horizontal directional drilling (boring).

 

 

NE Dunn Place & Chalmers Way

11/28/2022 Potelco Inc. has completed installation of the new conduit and vault system.  In the coming weeks, McMinnville Water and Light crews will be installing new underground power lines.  The installation of the power lines will require power outages.  Customers will be notified of outage dates and duration.


 

NW 2nd Street: Between Filbert & Hill Road.

The existing overhead power lines on NW 2nd Street, between Filbert and Hill Road, are scheduled to be upgraded. The upgrade will include the replacement and relocation of existing utility poles, installation of two new steel poles at the intersection of NW 2nd Street and Hill Road, the upgrade of the existing overhead conductors as well as installation of new underground power.  Magnum Power is scheduled to install the steel poles in early August of 2022.

McMinnville Water and Light is seeking bids from contractors for the installation of conduit and vaults.  The installation will be by means of horizontal directional drilling (boring).  We anticipate the contractor starting in January of 2023.

Please give us a call with any questions at (503) 472-6158. Thank you for your cooperation.


 

3 Mile Lane Bridge- Water Main Replacement

MW&L is installing 1,520 feet of new 12-inch ductile iron water main on the new 3 Mile Lane Bridge during construction. There is currently no water main along this route.

 

 


 

SW Brockwood Ave between SW Edmunston & SW Gilson St

  • MW&L is installing new 10-inch ductile iron water main in this area. We estimate work to be completed by April 15, 2022.

During the construction process curbside parking will be limited at times & there will be possible road closures and restrictions. We appreciate your patience!

Please give us a call with any questions at (503) 472-6158. Thank you for your cooperation.